3-Stage FERC Consultation Process Licensing and Relicensing Regulations

Date: 1991-01-01
Categories: Environmental Impacts
Source: Sustainable Living Library

Summary

Technical report. Covers Eastern U.S., Western U.S.. Topics: hydropower licensing process, pre-filing consultation, public participation, hydropower licensing. Agencies: Federal Energy Regulatory Commission, Forest Service, NMFS. Cites 13 external works.

Local Knowledge Graph (37 entities)

Loading graph...

Knowledge graph centered on 3-Stage FERC Consultation Process Licensing and Re with 37 nodes and 76 connections. Top connected: United States Forest Service, United States Bureau of Land Management, not specified, United States Environmental Protection Agency, National Park Service.

Stakeholders (18)

Agencies, organizations, and groups mentioned as actors in this document.

United States Forest ServiceUnited States Bureau of Land ManagementUnited States Environmental Protection AgencyNational Park ServiceFederal Energy Regulatory CommissionFERCFWSCommission
Show 10 more
COEFSstate fish and wildlife agenciesNMFSIndian tribesstate water resources management agenciesOffice of Hydropower LicensingOHLDPRRO

External References Cited (13)

Works cited by this document, grouped by type.

regulation (9)

  • Sections 4.92 and 4.107
  • Sections 4.93 and 4.105
  • Section 4.201
  • Section 16.8
  • Section 16.10
Show 4 more regulation
  • Section 375.314
  • Order No. 533
  • Order No. 533-A
  • Section 4.38

legislation (4)

  • NEPA
  • PURPA
  • Clean Water Act
  • Federal Power Act